SHAWANO — Build it right.
That was the consensus of a crowd of about 130 people who filled the chairs and lined the edges of the Shawano Lake County Park pavilion Wednesday for an informational meeting about a replacement bridge on County Road HHH.
The bridge, over what is officially called Shawano Creek but locally known as “The Channel” was built in 1951 and is scheduled for replacement in 2022.
What “right” is, and whether or not the Wisconsin Department of Transportation will be willing to support it, was the focus of the meeting. Gathering comments from residents and visitors about the design was another priority, according to Grant Bystol, Shawano County highway commissioner.
Design work for the new bridge is starting now, Bystol said. Keith Behrend and Tara Meyer from Strand Associates, an engineering design and consulting firm, also presented information about both the bridge design and how to register comments about it.
Bystol explained that a new rule from the state of Wisconsin Department of Transportation requires bridges to be “replaced in kind.” This means that the bridge is scheduled to be constructed to current standards, but without additional upgrades. For the HHH bridge, it would mean widening it to the 44-foot current standard for width, but leaving it at its current 5.6-foot height above water level.
The wider bridge will accommodate a lane for bicycles, pedestrians and snowmobiles, Bystol said.
With this approach, the state would pay 80% of the cost of the bridge, and the county would pay the remaining 20%, he said.
Anticipating that the current bridge level would be seen as too low for current boat traffic, a second option was presented that would both widen the bridge span and bring the height to 6.9 feet. This is roughly the same bridge structure that is over the channel on North Main Street (state Highway 47-55), Behrend said.
Raising the bridge would also mean some additional work, which would add to the cost, Behrend said.
Cost estimates for either option were not available, but Behrend acknowledged that the higher, wider bridge would be about one and a half to twice the cost of simple replacement.
Bystol said the county has agreed to cover the 20% cost of either option.
When the forum was opened to questions, nearly everyone who spoke addressed the need for a wider, higher bridge.
“I’m happy to see everyone here. This is a project that has been a long time coming,” said Clark Delzer, a Shawano-based Department of Natural Resources warden. “With safety in mind, the longer span is what I would vote for. I can’t tell you how many navigation lights I’ve snapped off on that bridge.”
Other questions involved the timeframe for the construction and impact on traffic. Bystol said every effort would be made to start the project after Labor Day 2022, but that the timetable was dependent on the weather.
North and south road traffic will need to be diverted to Highway 47-55 for much of the construction, but impact on boat traffic was expected to be much less, only a few days, according to Meyer.
Tony Zielinski, Shawano, said he owns “…a marina in the area, and four or five times a year, I get repairs, boats are jammed into this bridge. If you don’t duck you’re going to get decapitated. There are tremendous health and safety issues.”
Zielinski’s comments drew a round of applause from the crowd.
While safety was a repeated concern, the impact on tourism was also on the minds of many of those who attended.
“Tourism is a big factor in this community. If we don’t make it easy for people to do the things they want to do, they’ll go somewhere else,” Bob White said. “They can’t help how high the water gets, but they can plan for it.”
Comments like these were collected during the event, and comment sheets were distributed with a request to send comments to Strand Associates to compile and present.
“If we do not have public support we will be stuck with the ‘replace in kind’ option,” Bystol said.
Bill Monfre, a board member of Shawano Area Waterways Management (SAWM), said he plans to send the plans to the members of SAWM and ask them to send in their comments. He submitted written comments outlining the congestion and low clearance of the current bridge.
“We’re going to send comments to members and ask them to reference concept two (the expanded bridge design), with safety and matching the bridge on state (Highway) 55 as reasons,” he said.
Both residents and visitors are invited to submit comments about the bridge. Comments, and requests for electronic files with the bridge design options, can be sent to keith.behrend@strand.com.
Crowd voices bridge concerns