City officials Wednesday awarded bids for street and utility reconstruction projects that came in at significantly less than expected.
The Common Council approved the bid from Dorner Inc. of Luxemburg in the amount of $2.18 million.
Eight companies competed for this year’s street reconstruction projects, with the highest bid coming in at nearly $2.6 million, which was closer to expectations budgeted in this year’s capital improvement projects.
“We’re very happy with the bids the way they came in,” said Eddie Sheppard, city public works coordinator.
Some of the major street reconstruction projects for 2017 include Hamlin Street, from Fifth to Schurz streets; Franklin Street, from First to Third streets; and Franklin Street, from Oshkosh to Wescott streets; Division Street, from Hamlin Street to 500 feet east; Schurz Street, from Hamlin to 500 feet east; and storm sewer repairs on the north lane of East Green Bay Street, from Green Bay Court to Arlington Street.
The total cost will be split between street reconstruction at about $1.1 million and sanitary sewer and water main work at just over $1 million, a portion of which will be funded through the tax incremental finance district.