The long-awaited saddle replacement project on Main Street got underway this week, beginning north of Main Street up to Third Street for the first phase.
The entire project will cover Main Street from just south of the channel to the end of the 200 block of South Main Street.
At issue are stainless steel saddles (a type of metal sleeve) that hold the service connection to the water main. They were installed during the Main Street reconstruction project in 2002 and 2003. The project stretched from the channel to the Mountain Bay Trail at Oshkosh Street.
The Shawano Common Council approved borrowing up to $180,000 from the Shawano Lake Sanitary District to cover the cost of replacing 71 saddles along Main Street.
The loan will be paid back over a five-year period with an interest rate of 3 percent.
The project is being done by DeGroot Inc.
Funding for the project will come from the Department of Public Works’ water utility fund, though the utility will borrow the money from the State Trust Fund.
Main Street will remain passable during the project, but traffic will be cut to single lanes, with parking prohibited.
Public Works Director Scott Kroening said each phase of the project should take three to five days, depending on the weather.
Work south of Main Street should begin some time next week, he said.
Water will be cut off to most properties during at least a portion of the work day, but, Kroening said, public works and the contractor are working with businesses to make sure they have water when they need it and, in some cases, like restaurants and hair salons, ensuring they will have water at all times.
The project was supposed to take place last September, but due to weather and the contractor falling behind on other projects, the work was delayed until now.
A corroded saddle was blamed for a water main break outside Dreier Pharmacy at 117 S. Main St. on Jan. 4 of last year, the latest in a series of saddle failures over the last several years.
The city has been plagued with failing saddles since 2009.
Two water main breaks occurred in the 100 block of North Main Street in February 2009 and December 2010, only about 50 to 75 feet away from one another. Another saddle failed in the 200 block of South Main Street in September 2013.
It was determined that high levels of chloride in the soil were responsible for those saddle failures.
Random soil tests were done in 2015 by Mach IV Engineering, of Green Bay. Out of 20 locations sampled, chloride levels above 500 parts per million were found at three locations. Five others had chloride levels above 300 ppm.
The stainless steel used in the saddles could start to deteriorate at chloride levels over 300 ppm, according to city officials. At levels above 500 ppm, the deterioration is much faster.
Chloride levels in the area of the three previous water main breaks were in the range of 900 ppm, as a result of years of street salt seeping into the soil.
The new saddles, which will be brass this time, will be wrapped in heavy plastic, and additional backfill will be added to protect the saddles from the chloride.