The general contractor for Oconto County’s new Law Enforcement Center alleged in a federal lawsuit that the county unlawfully withheld funds for work the contractor had not agreed to do.
The suit filed Nov. 1 alleged:
• The contract Fabcor Inc., of Minster, Ohio, doing business as JAILS, signed in January 2016 to expand the LEC excluded the installation of certain security door frames. That work was to be done by another contractor. By June 2016, Fabcor and the county were in a dispute over which contractor should install the door frames.
• The dispute was submitted to the project construction manager, who initially decided that Fabcor was responsible for installing the frames. However, the manager resigned and instructed Fabcor that they would not be responsible for the frame installation or be charged the cost for another contractor to install them.
• Without giving Fabcor the required 10-day, the county contracted with another firm which installed the frames. The county subtracted $185,000 from Fabcor’s fee from payment despite Fabcor supplying materials for the project.
• Failing to give Fabcor notice precluded the contractor from acting to minimize its losses. The county also did not provide Fabcor the receipts for the costs the other contractor charged installing the frames.
• Despite the dispute and wrongfully withholding funds, Fabcor continued working on the addition, incurring another $57,000 in costs due to the delay the county caused in the dispute over installing the frames.
On June 16, Fabcor requested mediation of its claims pursuant to the contract but the county refused mediation, the lawsuit alleges. That refusal waived any requirements under the contract to settle disputes in mediation or arbitration, the company said.
In a Nov. 17 court filing, the county denied Fabcor’s allegations, contending Fabcor failed to complete its work and is not owed any money.
The county also alleged that Fabcor’s claims are subject to mandatory arbitration or are otherwise barred because the construction manager’s decision denying Fabcor’s claims is final.
Fabcor is seeking $242,000 in damages for the county’s alleged breach of contract and unjust enrichment.
Earlier this month, the county asked District Judge William Griesbach to compel the parties participate in mandatory arbitration. The motion remained pending Monday. If the matter does not go to arbitration, the county requested scheduling an August trial date for the suit.
The $31.2 million LEC includes a 94,000-square foot, two-story expansion that houses sheriff’s offices, jail support, emergency management operations and a 148-bed jail. County officials say the project is expected to be essentially completed as of Dec. 29.