The state’s Airport Road improvement project, initially pushed back to 2017, is back on again for this year, starting in August.
The estimated $2.5 million project will resurface and widen Airport Road from state Highway 22 to state Highway 29.
Shawano Public Works Coordinator Eddie Sheppard said the project, once expected to start in May of this year, was pushed to 2017 for funding reasons.
However, he said, the state saved enough money on other projects to move Airport Road up again to this year.
Work is expected to start in early August and take until at least mid-October, and no later than Nov. 1, to complete.
Sheppard said there will be a detour plan coming from the state, most likely making use of Highway 22.
The state is not permitted to submit a detour that doesn’t use state roads, though motorists might also unofficially be encouraged to use Waukechon Street as an alternative.
Pavement on Airport Road, which also is state Highway 47, has deteriorated, shows severe cracking and uneven surfaces, and has simply reached the end of its useful life, according to the state Department of Transportation.
The project will remove existing asphalt and add a new overlay the entire length of the project. Storm sewers inlet, curb and gutter, and signage also will be replaced where necessary.
Airport Road is a mix of two and four lanes, divided and undivided roadway. It will be reconfigured to a three-lane roadway with one travel lane in each direction and two-way left turn lanes.
The Airport Road and Green Bay Street intersection has a higher than average accident rate and planned safety improvement include the following:
• Adding left turn lanes in each direction.
• Modifying the median on the intersection’s southwest corner to accommodate turn lanes.
• Retiming traffic signals to optimize traffic flow.
At the Airport Road and County Road B intersection, plans include the following:
• Installing a four-way stop to reduce delays for County Road B motorists crossing or turning onto Airport Drive.
• Adding traffic islands and modifying medians to accommodate turn lanes.
The DOT calls the new roadway design an enhanced two-lane configuration, which creates shoulders between travel lanes and the curb, and also allows adding left turn lanes at Beauprey Road and Richmond Street.
Two-way, left-turn lanes added between intersections will provide access to adjacent properties.
A right turn acceleration lane will be added from Richmond Street to Airport Road as another safety measure.
Gates will be also added to the rail crossing due to inadequate sight lines. A curbed median will be added between opposing lanes of travel, and bus pullout lanes will be installed in each direction to improve traffic flow.
Six trains traveling at 40 mph maximum use the Airport Road crossing daily, and about 6,900 vehicles travel the roadway daily, according to the DOT.
Airport Road’s 45 mph speed limit will remain after construction is completed.