Preliminary plans for new sidewalks in Wittenberg appear to have support from the community as a public hearing on Aug. 7 only generated a couple of questions from someone affiliated with a snowmobile club.
The village received a grant in 2022 from the Wisconsin Department of Transportation’s Alternative Transportation Program that will pay for 80% of the cost to install seven new sidewalks, estimated to cost around $920,000.
New segments are:
• North Genesee Street from north of Grand Avenue to East Wood Avenue, east side.
• East Grand Avenue from North Meisner Street to South Mission Street, south side.
• South Webb Street from School Street to Washington Park, north side.
• East Vinal Street from South Mill Street to Pond Park, south side.
• Pond Park from South Mill Street to East Vinal Street.
• South Ellms Street from north of Walnut Street to Reed Street, east side.
• West Reed Street from Homme Home to South Mill Street, south side, and along South Mill Street to Park Pond, west side.
The project is expected to create about 4,715 feet of new concrete sidewalk in Wittenberg, according to Mary Jo Miller with Martenson and Eisele. She said the majority of the sidewalk will be five feet wide, but for places where there’s not a grassy buffer and they’re adjacent to a curb, those sidewalk segments will be six feet wide.
“The intent is to connect some empty segments of sidewalks to make a more continuous system,” Miller said.
She noted that the Pond Park sidewalk will be a particular benefit for residents and visitors to get around.
“It’ll be a nice connection for somebody who wants to make that shortcut through the park with a stroller or bike or something,” Miller said.
Dave Schmidt, a representative with the Wittenberg Trailblazers Snowmobile Club, only expressed concern about the sidewalk going on Reed Street because it intersects with a snowmobile trail. He noted that snow is removed from sidewalks during the winter months, which would impact the trail if the village plans to treat Reed Street the same.
“There are probably not that many people going from Homme Home to the park in the wintertime, I wouldn’t believe,” Schmidt said.
Wittenberg Village Board President William Switalla pointed out that concessions could be made for the snowmobile club, suggesting removing a couple of trees so that snowmobilers wouldn’t have to connect with the sidewalk.
Board member David Timm pointed out that, even with the trees removed, there might be other places where the snowmobilers might have to cross the sidewalk to continue on the trail.
“There’s other places in town where you must cross the sidewalks,” Timm said to Schmidt.
Miller pointed out that the sidewalks have a thickness of four to six inches, which shouldn’t be impacted by the weight of snowmobiles and riders.
Schmidt said he didn’t have any problem with the sidewalks, as long as it didn’t cut off snowmobile access.
“I guess we have to play it by ear,” Schmidt said. “I just wanted to make you aware. We don’t want to have to get shut off completely. That’s our main thoroughfare for south to north, people.”
Timm assured Schmidt that was not going to happen.
“That’s got to keep going,” Timm said. “It was never our intention to shut the trail off or restrict it in any way, to try and work around it.”
Miller noted that the earliest the project work could begin would be in July 2024, but because of legal red tape, it seems more likely that the sidewalks would be coming in 2025.
“It depends on how quickly DOT reviews all of this stuff,” Miller said. “They are extremely slow.”
The project will require the village to get one permanent easement from a property owner and temporary 10-foot easements from others, according to Miller. Topsoil will be removed, and there will be some grating, but there is no deep excavation required, she said.
“We’ve got some minor storm sewer improvements in three areas,” Miller said, noting culverts for Pond Park and near the Wiouwash Trail and some work around Wittenberg Sentry Foods will be required to complete the project.
lpulaski@newmedia-wi.com
New sidewalks coming in 2024, possibly 2025