The name of the new Oconto Falls middle school will be Oconto Falls Middle School.
The school board voted Aug. 14 not to retain the name Washington Middle School for the new structure, which is due to open in the fall of 2025. Voters approved replacing the aging middle school in a $37.3 million referendum last November.
The question of the school’s name was brought up at the July board meeting and placed on the agenda for a decision this month. Superintendent Dean Hess said changing the name will entail changing a variety of things from forms and letterhead to the uniforms worn by student athletes.
“The things that we miss will irritate people, but we’ll work through it,” Hess said. “It is what it is.”
Hess acknowledged that there is sometimes confusion, at interscholastic tournaments for example, whether a reference to Washington Middle School is to the one in Oconto Falls.
“It was brought to me that if it was Oconto Falls Middle School, then there’d be no question if you were in the right place or not,” he said.
The other argument in favor of the name change was consistency — the other district buildings are called Oconto Falls High School, Oconto Falls Elementary School and Abrams Elementary School.
“I like the idea of a more universal, community-type name,” said board member Bryan Baumler. “Washington obviously has history and things like that behind it, but it can be a little ambiguous.”
Board member Sarah Schindel asked if it was called Washington Middle School after Founding Father George Washington or simply because it’s located on Washington Street.
“Nobody knows,” longtime board member Ken Harter said. “I asked that question years ago.”
Hess said title documents show a number of names — the structure began life as Oconto Falls High School — but the question of why it got the name Washington is apparently lost to history.
Board member Emilie Trudell said changing the name would add work for the administrative team but she found a lot of community support for the change.
“In talking in the community, it seemed very, ‘Well, why wouldn’t you call it Oconto Falls Middle School?” Trudell said. “I got a lot of that and also a lot of comment that ‘Washington Middle School’ is tied to that particular building.”
Board President Clint Gardebrecht said the matter has received a lot of conversation and urged the board to make a decision.
“Unless someone has a violent objection, I don’t think we need a deep philosophical discussion on this,” Gardebrecht said.
At that, Carrie Hill moved that the new building be Oconto Falls Middle School, Baumler seconded the motion, and it was passed on a unanimous voice vote.
Earlier Brent Warren, director of construction management for Nexus Solutions, briefed the board on the latest round of bids for construction of the new school. The latest bid package included companies interested in doing site work including footings for the new building, as well as utilities into the site such as the water main, sanitary and storm sewers and bringing natural gas into the building.
The five bids, which the board approved, totaled $3.421 million, which is $131,870 or about 4% over the original budget for this phase of construction, which Warren said is good news.
Over budget is not ideal but this particular overrun is “not catastrophic,” Warren said.
“This is a small amount of money for what the grand scheme of this whole project is,” he said. “This day and age, with inflation, the construction industry the way we are, to be under 5% is good news. I’m ecstatic, I think that’s great. That’s 0.3% of the whole referendum; that’s not a lot of dollars.”
Warren also asked the board for flexibility in authorizing change orders. He recommended giving the administrative team the authority to approve change orders up to $25,000, with larger amounts needing the board’s OK.
“The intent of this is to try to avoid a situation where a decision is timely in nature and they’re wanting to make that decision within a couple days, and we don’t have a board meeting for two or three weeks,” Hess said.
There was some discussion whether to change the limit to $10,000, but ultimately the board agreed with the recommendation on a 6-1 vote, with board member Chad Earley dissenting.
The main bids for the project are due in September and October. Warren said the job trailer, where the project manager and crew will be headquartered for the next two years, arrived on site the morning of Aug. 14 and construction should begin in earnest in September.
“We ought to be pouring concrete by mid-October,” Warren said.
The plan is to complete the building by June or July 2025 to give the district staff time to move in by the start of the 2025-26 school year.
A handful of smaller projects approved in the referendum has been completed, Warren said. Secure entrances to the high school and elementary schools will be ready when classes begin Sept. 5, and roof work at the high school and Abrams Elementary School is finished. The roof of Oconto Falls Elementary School is on tap for the summer of 2024.