WITTENBERG — Preparation for the Webb Street reconstruction project started last week with the arrival of a work crew from WEC Energy Group, the parent company of WPS.
“Our work on Webb Street involves replacing our existing natural gas main and service lines between Reed Street and College Avenue,” said Matt Cullen, senior communications specialist at WEC. “This project is part of our focus on regularly upgrading our facilities so we can continue providing safe, reliable service to our customers.”
According to Cullen, the crew should complete its part of the project by mid-April.
Construction for a new road, sidewalk and gutters will begin in May and finish by the end of September. The portion of South Webb Street being reconstructed is between Reed Street and College Avenue. The plan will allow for local access.
Abby L. Maslanka, a project engineer, works for Martenson and Eisele Inc., the company in charge of the project. She noted that utility and road construction companies are considered essential businesses and are allowed to continue to operate under the “critical infrastructure” exemption.
“The schedule and sequencing will be set following discussions with the contractor, subcontractors and village of Wittenberg representatives,” said Maslanka. “The first step is ensuring the gas lines are installed and online.”
Maslanka noted that what happens next depends on the availability of the contractors. Martenson and Eisele will also closely monitor the situation regarding the current safety and social distancing standards set by the governor in regard to the COVID-19 virus.
Crew replaces gas line on Webb Street