New sidewalk segments for Wittenberg are definitely on hold until at least 2025, officials confirmed Sept. 19 during a village board meeting.
Village Clerk Traci Matsche told the board there is no way the village will be able to begin work in July 2024 on creating new sidewalks due to the hoops that the state is making local government officials jump through. The village received a grant in 2022 from the Wisconsin Department of Transportation’s Alternative Transportation Program that will pay for 80% of the cost to install seven new sidewalks, estimated to cost around $920,000.
“With the DOT, there are specific steps that you need to take, and each step has to be approved by them before you move on,” Matsche said. “First, it was environmental, which was sent in April, and it still has not been approved. At this rate, there’s no way to get the design phase approved in time to even do bidding for a July start.”
Matsche noted that, even with the delay, the state funding will be available if the work begins in 2025. The only caveat is the work has to begin by 2026 and be completed by 2029, she said.
“This is ridiculous,” Matsche said. “It’s like pulling teeth to get them to respond, much less approve anything.”
She added that it might be possible to get bidding for the projects done in 2024, but it would likely be too late in the year for work to begin.
DOT is also changing requirements for determining easements with the project. Matsche said that she and Mary Jo Miller with Martenson and Eisele had gone out and conducted measurements themselves for a previous project, but DOT requires that the easement work be contracted out.
“That’s more expense on us that we didn’t know about,” Matsche said.
She added that engineering costs are expected to go up, at village expense, because of all the changes that DOT is requiring Wittenberg to make.
“We’ll get the project done, but it’s going to cost us a little bit more on our part of it, and we don’t know exactly when we’ll be starting,” Matsche said. “We don’t get it. They’re treating us like some big city project. We’re just a tiny little burg, and it’s just a sidewalk project, for God’s sake.”
New segments of sidewalk for the village include the following:
• North Genesee Street from north of Grand Avenue to East Wood Avenue, east side.
• East Grand Avenue from North Meisner Street to South Mission Street, south side.
• South Webb Street from School Street to Washington Park, north side.
• East Vinal Street from South Mill Street to Pond Park, south side.
• Pond Park from South Mill Street to East Vinal Street.
• South Ellms Street from north of Walnut Street to Reed Street, east side.
• West Reed Street from Homme Home to South Mill Street, south side, and along South Mill Street to Park Pond, west side.
Matsche expressed her frustration with how slow the process has been.
“We’re never going to get a DOT grant again,” Matsche said. “This has been a pain in the butt.”