A task force studying elementary school needs in the Clintonville School District this week recommended that the district ask voters for a new school in the April 2017 election.
Task force members Amanda Gross and Larry Czarnecki presented the group’s recommendation to the board Monday. It calls for a $24.9 million referendum.
According to the school district, the plan would include a tax increase of no more than $98 per year for the owner of a $100,000 home for the first five years; the rate would decline after that.
The board is expected to vote on the recommendation when it meets at 6 p.m. Nov. 28.
The committee’s recommendation is to construct a new elementary school to house students in 4-year-old kindergarten through fourth grade, to close the Dellwood Early Learning Center, and to demolish Rexford-Longfellow Elementary School and the adjacent 1918 structure that at one time was the high school.
Last month a survey conducted for the school district found more residents support building a new elementary school than remodeling the current elementary school.
District officials say the 1918 section of the complex needs tuck pointing, the windows and doors need to be repaired or replaced, a portion of the roof needs to be replaced, the heating system is aging and parts of the building do not meet Americans with Disabilities Act standards.
The Rexford-Longfellow building infrastructure does not support current technology, according to a facilities assessment done by Bray Architects. The building is larger than what is needed to serve the current and projected student enrollment and is more expensive to heat and operate due to age.
Matt Wolfert, architect with Bray Associates, told those attending the meeting Monday that they should trust the survey data but not be complacent.
“This is not a slam dunk, there is a lot of work to do,” he said.
School Perceptions conducted the survey for the district in October. The response rate was about 21 percent, with 1,150 surveys returned.
When asked if they would support a $19.6 million to $23.7 million referendum to renovate Rexford-Longfellow Elementary, 37 percent of the survey respondents said no; 36 percent said yes.
When asked if they would support a $24.9 million referendum to build a new school on the existing Rexford-Longfellow site, the vote was 50 percent yes and 33 percent no.
There were substantial numbers of people undecided or wanting more information about both questions.
The “undecided” is the nice way that people say no, Czarnecki said, adding that if the district were to pick up one-third of the undecided voters, there would be a 51 percent likelihood of the referendum passing.
In 2022, the district will make the final payment on the debt issued to build the high school and recreation center.
The task force consists of 31 members, including parents, district staff and residents. They have held nine meetings since April.