The City of Clintonville will study the option of a swim pond.
Upon recommendation of Park and Recreation Director Justin McAuly, the members of the Park and Recreation Committee voted Wednesday to ask the finance committee to approve spending $4,150 to generate a basic concept plan for a swim pond. The money would come from current funds that are in a pool fund.
“Once we get a green light for funding, we will be able to generate a much more detailed plan that could be presented for community interest,” McAuly said.
Of that amount, $3,400 will go to Commercial Recreation Specialists and $750 to Wisconsin Lake & Pond Resource LLC.
Voting yes were Steve Kettenhoven, Chuck Manske, Carol Metzger and Jim Supanich. Don Jirschele was absent.
At an October meeting of the Park and Recreation Committee, McAuly presented the idea of installing a man-made swimming pond in lieu of a swimming pool. He outlined several swimming lakes in surrounding areas. He also presented a proposed design for a lake located in Bucholtz Park, over the area where the pool is currently located.
McAuly stated that a swim lake, rather than a pool, could be multipurpose and meet the communities needs. Cost and location were discussed. At that time, City Administrator Sharon Eveland said it was important for the committee to decide how they plan to move forward with or without a swimming facility.
The outdoor pool has been closed for several years after a fire destroyed the pool house. The cause of the fire has not been determined.
During the citizen forum portion of the meeting, Dennis Lichtenberg told the committee that they really need a plan to move ahead and at least come to a decision.
“If there is no plan, it won’t move ahead. You don’t need funding in place to apply for a grant,” Lichtenberg said.
He said a plan consists of determining an estimated cost, applying for a grant, implementing a fundraiser, and getting city approval for any remaining funds needed. He thought a three-year plan would be reasonable so the city can plan ahead when city funds for the pool or pool pond may be needed.
Lichtenberg had done extensive study on grants.
“Most grant deadlines are around May for the year you’re applying for a decision by fall,” he said. “The state DNR Knowles-Nelson Stewardship Program, which works with the federal and and Water Conservation Fund, would be a good place to start.” Matching funds would be needed from the city.
“I appreciate your work but the city is facing $500,000 shortage in the capital budget over the next three years without the pool,” said Jim Supanich, alderman and member of the Finance and the Park and Recreation Committee. “Where is the money to come from? We are still looking at options for the pool. It is not a sure thing but there are some limitations.” Supanich pointed to the street repairs, a new fire truck, and city facilities that will need funding.
“You can find cities smaller than Clintonville that have a pool,” Lichtenberg said.
“We are still working through the process. We are looking for something reasonable. We’ll move ahead but unless it looks very viable, it might be June before we decide,” Supanich said.
Committee chairman Steve Kettenhoven said,”Whatever way we go, we have to apply for grants.”
McAuly reported that a modified plan for a swimming pool is estimated at $2.8 million by Wisconsin Water Technologies.
The city has approximately $130,000 from fire insurance and about $35,000 that has been set aside for a swimming pool project.