The Oconto Falls City Council gave final approval to plans to rebuild a stretch of Adams Street on June 12, and the project was in full swing by the end of the week.
Aldermen held a public hearing on the improvements before their regular monthly meeting, drawing a couple of dozen residents but only a handful of questions about the details of the project.
The work covers an area of Adams Street from Monroe Street to Union Avenue, where Washington Middle School is on the corner.
In addition to replacing the street and underlying water and sewer mains, the project includes sewer updates, driveway aprons, curbs, gutters and sidewalks. Quotes for installation for those items amount to approximately $260,000, City Administrator Vicki Roberts said.
Of that total, homeowners will be responsible for between 20 and 100 percent, Roberts said. She shared a spreadsheet showing how much each individual property owner will be billed.
The city’s cost for the main work was expected to be close to $500,000, but that will be offset by a state grant of $263,704, she said.
Roberts got quotes from three banks on financing up to $550,000 for Adams Street and a new tractor for the street department, but the grant greatly reduces the need to borrow.
The council added a long-delayed fix of Cherry Avenue, estimated at $62,000, to the borrowing package before approving Peshtigo National Bank’s low bid on a seven-year fixed loan for 2018 construction projects. The final loan amount is still to be determined, but thanks to the grant, it will be far below the original $550,000 request, Roberts said.
There was some question during the public hearing about removing trees along Adams in the right of way, but city officials said that’s needed to prevent future damage to the new curb and sidewalks.
“There’s a reason we took ‘em out – we did it on Union, too, and Cedar,” Mayor Brad Rice said.