The Oconto County Board unanimously approved change orders Thursday on the law enforcement center construction project because of delays in the delivery and installation of materials.
County Administrative Coordinator Kevin Hamann said the total cost could reach $150,000 for changes in construction on portions of a new jail in the law enforcement center.
The first change order approved Thursday by the County Board was for $41,566, which will be the last payment to install detention frames in the new jail cells.
The second change order was for $16,488 to install temporary doors and windows on the outer entrances to the new structure.
“Because of delays in the project, we had to get some temporary doors and windows installed to make it at least bearable inside so they could work,” Hamann said.
The county’s contract for detention doors and frames is with Fabcor Inc., of Minster, Ohio. But another contractor, Zeise Construction, was hired for part of the work after what Hamann described as a disagreement with Fabcor.
“At the end of the project, we will probably be going to arbitration and trying to resolve it,” he said.
The law enforcement center, which is under construction next to the Oconto County Courthouse in Oconto, includes a new jail, sheriff’s department office and 911 dispatch center. The estimated $31.75 million project is scheduled for completion by Labor Day.
Officials reported another delay Thursday that prompted them to seek a variance from state regulators to continue with installation of ceilings inside the jail.
Tim Harmann, a representative of The Samuels Group, a consultant on the project, told board members that earlier efforts at reducing costs on the project led an engineer to recommend reducing the amount of conduit installed to encase wiring in the ceilings.
But state building codes require a variance from the state to reduce the conduit.
Hamann estimated that correcting the conduit issue could cost $50,000 to $100,000 if no variance is granted. Hamann said Oconto’s fire chief had signed the variance on the condition that it also be approved by the state.
“Oconto County thanks the city of Oconto fire chief for his conditional approval and his extra efforts in contacting state inspectors regarding our variance request,” Hamann added.
Until the variance issue is resolved, ceilings cannot be installed in certain areas.
County Board members also approved the purchase of $127,556 in technical equipment for the new law enforcement center. The equipment includes fingerprinting stations, Wi-Fi access points, copy machines, phones, computers, printers, cameras and more.
“These are things that are necessary,” Hamann said. “This was all planned for.”
With the move of the sheriff’s department into the law enforcement center, the county’s technology services department will move into the sheriff’s vacated space.
The board approved hiring Architects Group Limited of Green Bay to prepare plans and specifications for remodeling the sheriff’s old space at a cost of $5,665.