Shawano’s Main Street saddle replacement project that was supposed to start this week has been delayed until spring, according to Public Works Coordinator Eddie Sheppard.
DeGroot Inc., which had been contracted for the project, had gotten held up on other work elsewhere due to rain and was about two weeks behind schedule, Sheppard said.
Sheppard had been in contact with DeGroot for much of Wednesday to nail down a new timeline for the Shawano project in the hope that it could get underway next week.
By day’s end, it was determined that wouldn’t be feasible.
Sheppard said the city and DeGroot are now looking at the project taking place in late April or early May.
“We’re working that out with the contractor right now,” he said.
The project had been planned to work around and not interfere with upcoming events, including the Octoberfest festivities hosted by the Business Improvement District on Oct. 6, as well as the Bike the Barn Quilts event and Homecoming parade.
It was expected to be wrapped up by the end of October, and downtown businesses were already preparing for periods of water being shut off and promoting parking behind their businesses.
“In the interests of making sure we can get it all done and sealed up, just as we were looking at the schedule, I think it’s best if we pushed it to next year,” Sheppard said.
A new schedule will be shared with business owners and Main Street residents once the specific spring dates are nailed down.
At issue are stainless steel saddles (a type of metal sleeve) that hold the service connection to the water main. They were installed during the Main Street reconstruction project in 2002 and 2003.
The city has been plagued with failing saddles starting in 2009. Most recently, a corroded saddle was blamed for a water main break outside Dreier Pharmacy at 117 S. Main St. in January.
Two water main breaks occurred in the 100 block of North Main Street in February 2009 and December 2010, only about 50 to 75 feet away from one another. Another saddle failed in the 200 block of South Main Street in September 2013.
It was determined that high levels of chloride in the soil were responsible for those saddle failures.
The new saddles, which will be brass this time, will be wrapped in heavy plastic, and additional backfill will be added to protect the saddles from the chloride.