Shawano Municipal Utilities received approval this month from state utility regulators to build a $12.9 million service center on the site of its aging and inefficient facility.
Demolition of the existing 21,000-square-feet facility at 122 N. Sawyer St. and 213 E. Green Bay St. will begin in late July or early August, with construction expected to begin in September, said Bruce Gomm, SMU general manager.
Construction should be completed by early fall 2024, giving SMU a 29,000-square-foot, modern facility that betters serves its employees and customers, Gomm said.
“The existing service center isn’t ADA-compliant. The garage isn’t big enough to hold all our vehicles and materials, which should be inside, and security is another big issue. There’s no way to secure parts of the building,” Gomm said.
Some portions of the service center are 90 years old; with additions constructed in 1959 and 1986, according to the Public Service Commission construction authorization order issued June 13.
During the past 20 years, SMU acquired nearby lots in anticipation of working out of a larger facility.
A new service center has been in the planning stage for years.
A space needs assessment in 2017 found deficiencies in the service center’s, roofing, heating and ventilation systems, doors, windows, pavement and other components requiring imminent replacement of significant repair.
Instead of rehabilitating the center or, moving out of downtown, it was decided to build a better center, Gomm said.
A 100-kilowatt solar array will be added to the roof, expandable but currently sized to generate enough power for much of the building’s needs.
Wells dug 150 feet deep will be part of the geothermal system to heat and cool the building.
The new center will have a stormwater management plan and facilities, something that current one lacks.
The current center’s employee kitchen is the only room large enough for staff meetings, training sessions and Utility Commission meetings. The second-floor customer service area isn’t an ideal location.
The Utility Commission will consider giving final authorization to the project at its June 26 meeting.
The new center will have a first-floor customer service area, staff offices, training rooms, field crew rooms, vehicle and equipment garage, and warehouse space.
It’s sized large enough to accommodate some future growth, according to the construction application.
The utility will issue a bond to finance construction and then file a rate case, probably yet this year, to increase revenue to repaid the bond. Gomm said.
In January, it was estimated that the project’s cost would result in a 5.5% overall increase in electric rates.
Earlier this year, the PSC authorized a 1.35% increase in residential electric rates bringing monthly electric bills to $84.25. A 5.5% increase would boost the bill to $88.88.
SMU gets green light for new service center