Shawano County will spend more than $800,000 on its capital improvement plan next year, after supervisors voted Sept. 27 to adopt the 2024-28 plan.
All three major projects slated for 2024 in the five-year plan revolve around the Shawano County Sheriff’s Department and jail.
Modernization of the jail elevator is projected to cost $146,000, with federal ARPA funds used to cover the cost. Replacing the sheriff’s department and jail control system will cost an estimated $415,000, and will be paid for by a mix of money from the Ho-Chunk Nation, environmental impact, sales tax and federal programs. Finally, the $200,000 needed to replace the shower and restroom floors in the dorms will be paid from the inmate welfare fund.
“Levy limits, unfunded mandates and the need for the county to provide services to our citizens in need, leaves little revenue to be used as a source to fund capital projects,” said Jim Davel, the county’s administrative coordinator, about the plan. “Capital needs and project costing will continue to increase exponentially if we do not address these needs on an annual basis.”
The entire plan focuses on building improvements outlined through the recently completed facilities assessment. For example, replacing the control system in the sheriff’s department and jail, as well as replacing the shower and restroom floors in the dorms, were recommended as priority one projects in the facilities assessment report.
Several other priority one projects, totaling $76,594, are part of the 2024 plan. These projects are all at the sheriff’s department and jail and include replacing leaking sanitary pipes, replacing deteriorated storm piping, and replacing the ceilings in the kitchen, booking room and squad room.
It is understood the amounts listed in the 2024 plan are to be incorporated into the Shawano County budget for 2024, with subsequent annual amounts subject to change in the future.
Future projects include:
• $229,000 for a new roof on the Crawford Center (TBD).
• $750,000 to replace two old maintenance shops with one large enough to store all equipment (TBD).
• $91,750 for the remaining priority one maintenance projects listed in the facilities assessment (2025).
• $10.96 million to $12.37 million to renovate the public library (TBD), unknown costs to update the county’s fiber infrastructure (TBD).
• About $1.67 million for priority two maintenance projects at the courthouse, heating plant, sheriff’s department and jail (2025).
• About $1.16 million for priority three maintenance projects at the jail, courthouse and heating plant (2026-28).
• $396,900 for priority four maintenance projects at the courthouse and jail (2028-33).
• $173,000 for priority five maintenance projects at the sheriff’s department, jail and heating plant (2033).