The Oconto Falls City Council voted June 13 to amend the budget for the new fire station to reflect higher than anticipated costs.
The city last year obtained a $7 million Neighborhood Investment Grant from the state Department of Administration to build the new station using federal funds, but bids this spring came back about 10% higher than expected.
A planned groundbreaking ceremony was postponed while construction manager Zeise Construction, city, fire department and architect worked on ways to reduce the total project costs, City Administrator Peter Wills said.
About $200,000 in savings were found, and the City Council approved an amended $7.5 million budget, Wills said.
“Zeise Construction will begin preparing to begin construction, and we will be setting a new groundbreaking for the station in the next few weeks,” he said.