Traffic began flowing again July 12 along state Highway 22 between Oconto Falls and Stiles Junction, four months after the road was closed for a major reconditioning project.
When the road was closed in early March, the state Department of Transportation had estimated the work would take until mid to late August.
“All in all they’re five weeks ahead, which is amazing given the wet summer we’ve had,” City Administrator Vicki Roberts said.
The 4.22-mile, $3.4 million project involved milling the existing asphalt pavement and placing a new driving surface between Highland Drive just inside the Oconto Falls city limits and Duame Road just west of the U.S. 141 interchange.
Other work included adding right-turn lanes at County Road I, Larson Road and Younger Road, removing and replacing two concrete box culverts, replacing existing culvert pipes at various locations, and installing new pavement marking and permanent signs.
Drivers and residents were allowed access to businesses and homes along the highway, but traffic was officially detoured north along County Road I or U.S. 141 to County Road A. Unofficially, many drivers used County Road I south between Oconto Falls and Stiles.
Early on July 12, the contractor completed installing permanent signs, and the highway was opened to traffic around noon.
Workers have not completely left the area; the contractor this week expects to complete grubbing stumps and restoring those areas and finishing roadway items. The work is expected to be done from the roadway shoulder, and flaggers may occasionally be used to divert traffic around the work area.